Construction of Matarbari Port Development Project is progressing as scheduled, with around 3.6 million cubic metres of dredging already completed, Shipping Minister Shaikh Rabiul Alam told parliament on Tuesday.

“Of the three main packages of the Matarbari Port Development Project, works on two packages have already started,” he said in response to a written question from treasury bench lawmaker Mohammad Mazharul Islam (Kishoreganj-1) in Jatiya Sangsad today with Speaker Hafiz Uddin Ahmad, Bir Bikrom, in the chair.

Explaining the progress of Package-1, titled Civil Works for Port Construction, the minister said the project authorities issued a Notice to Proceed (NTP) to the contractor, PT JV, on August 31, 2026, to begin the construction work, BSS reported.

He said the necessary equipment for land reclamation had already arrived at the project site.

“Construction of Geotube embankments, dredging, sand filling in Areas A and B, and CDM works are continuing,” he said, adding that approximately 3.6 million cubic metres of dredging had been completed so far.

Regarding Package-2A, covering equipment, the Terminal Operating System (TOS) and security systems, the minister said the design and drawing preparations for various equipments by the contractor, Mitsui E&S and Tec International Consortium of Japan, had reached the final stage.

He said a factory survey was conducted in Japan from April 4 to 11, 2026, to assess the equipment manufacturing capacity.

On Package-2B, covering boats and the Vessel Traffic Management and Information System (VTMS), the minister said a meeting with a JICA delegation was held at the Ministry of Shipping on September 2, 2026.

“The meeting decided to seek the bidders’ opinions on extending the tender validity period and bid security, as well as reducing the scope of the tender (descoping), to expedite the procurement process for Package-2B,” he said.

The minister said the project, once implemented, would enable large container vessels with a capacity of 8,200 TEUs to berth at the port’s jetty.

Responding to a question about delays in establishing the seaport, Shaikh Rabiul Alam said the port’s activities were continuing by following the prescribed procedures.

“The implementation period for the establishment of the seaport extends until December 2029. Therefore, there has been no delay in its establishment.” he said.