Electricity from the first unit of Bangladesh’s largest renewable energy source – the Rooppur Nuclear Power Plant (RNPP) – was experimentally connected to the national grid on Tuesday, 17 November 2026, delivering 350 megawatts starting around 3:00–3:16 p.m.

Science and Technology Minister Fakir Mahbub Anam was present for the milestone.

The connection follows months of sequential technical work and testing. On 29 October 2026, the Bangladesh Atomic Energy Regulatory Authority (BAERA) approved the start of the “Power Startup Stage-C” phase. During this stage, reactor power has been raised gradually to check turbines, generators, safety systems and grid coordination. Earlier reports had projected an initial trial supply of roughly 240–300MW; the actual figure reached 350MW.

The unit is currently operating at only about 3 percent of capacity, with output to be increased in stages.

Under the approved plan, power will be fed into the grid for about 8–10 hours while engineers monitor turbine and generator performance, system stability and coordinated grid operation. The plant will then be disconnected for roughly 28 hours. After that interval it will be reconnected for another 4–6 hours to complete further technical and operational checks. Each stage’s results will be reviewed; continued trial operation requires additional BAERA approval.

Per the contract with the Russian contractor, successful completion of a 10-month trial-operation period will lead to the provisional takeover of the first unit by the Bangladesh Atomic Energy Commission and the start of permanent commercial supply at full capacity. A government gazette notification will then designate Nuclear Power Plant Company Bangladesh Limited (NPCBL) as the operating organisation. Some earlier reports had targeted a more permanent grid connection around 21 November, subject to test outcomes.

Rooppur has two Russian VVER-1200 reactors, each rated at 1,200MW (2,400MW total). Construction began with the first concrete pour for Unit 1 on 30 November 2017 and for Unit 2 on 14 July 2018.

Recent fuel deliveries, including a sixth uranium shipment, have continued. Once both units reach full operation, the plant is expected to contribute substantially to meeting growing electricity demand and improving long-term energy security. Officials have emphasised that the current connection is a trial step for system verification and does not yet constitute commercial operation.